Umahi Terminates Benin–Warri Road Contract, Seeks Refund

Published

on

The Minister of Works, David Umahi, has terminated the contract awarded to Levant Construction Limited over its failure to deliver on the Benin–Sapele–Warri road project.

The road, a major federal highway, is being reconstructed under the Road Infrastructure Development and Refurbishment Investment Tax Credit Scheme.

Advertisement

Speaking in Abuja after a meeting with contractors handling various sections of the project, Umahi accused Levant of abandoning its section of the road despite multiple warnings and a final termination notice.

According to a statement signed by his media aide, Orji Uchenna, on Wednesday, the minister disclosed that despite intervention by the Edo State Government on the worst sections of the road, Levant failed to mobilise to its portion of the site, leaving critical areas unattended.

We even begged the Edo State Governor to fix the worst-hit parts while Levant handled the remaining. While the governor delivered on his 23km stretch for N35bn, Levant abandoned its section.

Advertisement

“They received multiple warning letters, including a final notice, but chose not to return to the site,” Umahi said.

READ ALSO: Drama As Woman Accuses Umahi Of Sexual Harassment, Unpaid Contract, Minister Threatens Legal Action

Umahi directed the Permanent Secretary to finalise the contract termination, initiate a joint measurement for completed works, and write to the company’s bank for the recovery of the Advance Payment Guarantee.

Advertisement

He warned that failure to refund the public funds could lead to prosecution by the Economic and Financial Crimes Commission.

In contrast to Levant’s performance, the minister praised Geld and SKECC for agreeing to return to the site following renegotiations.

He noted that a project review has been approved to accommodate inflationary pressures, including the rising cost of asphalt, now pegged at ₦30,000 per square metre from a previous ₦9,000.

Advertisement

“I’m pleased with Geld’s commitment. For their other job on the Lokoja-Abuja road, we’ve agreed to a price review. The same applies to the Itoki–Ikorodu road. We are happy to see movement again,” he said.

He also lauded the efforts of Delta State Governor, Sheriff Oborevwori, and Edo State Governor, Monday Okpebholo, for stepping in to fund critical sections of the federal road.

We are grateful. These governors are doing very beautiful work,” he said.

Advertisement

READ ALSO: 52% Of Ongoing Road Construction In Northern Nigeria – Umahi

Reacting to recent claims by some Northern groups accusing the Tinubu administration of favouring the South in road projects, Umahi described the allegations as “malicious and uncharitable”.

He stressed that project distribution under President Bola Tinubu’s Renewed Hope Agenda has been fair, inclusive, and based on inherited commitments and current needs.

Advertisement

In this ministry, we don’t count regions. We follow the President’s example—he inherited projects and chose to continue them irrespective of location,” Umahi said, citing the Abuja–Kaduna–Zaria–Kano road project as a case in point.

He noted that under the NNPC Tax Credit Scheme alone, Niger State accounts for 26 per cent of the project portfolio, while the South-West and South-East combined barely get 9 per cent.

In his detailed response, Umahi listed several ongoing projects in the North, including the Abuja–Kaduna–Zaria–Kano road (Sections I & III) worth N252bn, with 30 per cent already paid.

Advertisement

He said, “Section II of the same highway, 164km long, valued at N525bn, with another 30 per cent (N152bn) already disbursed. Sokoto–Zamfara–Katsina–Kaduna 750km road at N825bn, started under President Tinubu.

“There are Dangote-backed Tax Credit projects in Borno, including 49km in Bama and 52km in Dikwa. The N958bn dual carriageway project in Kebbi, with a second phase heading to FEC for approval. The 439km Akwanga–Jos–Bauchi–Gombe superhighway is being redesigned to a six-lane concrete pavement on Tinubu’s directive.”

READ ALSO: How Obaseki, Umahi’s Intervention Is Addressing Deplorable State Of Ekpoma – Abuja Federal Highway

Advertisement

He added that under the Renewed Hope legacy projects, the North is receiving 52 per cent of the investments, while the South gets 48 per cent.

On the controversial Lagos–Calabar Coastal Highway, Umahi said the project is not designed to favour any region, explaining that comparable investments are being made in the North with the same quality and cost standards.

“For instance, the Kebbi section alone, with just one carriageway, is costing about N958bn. When the second lane is approved, that’s nearly N2tn—comparable to Lagos-Calabar segments,” he said.

Advertisement

Addressing criticisms on the slow pace of work on the Eleme–Onnexis of the East–West Road, Umahi said the contractor, RCC, has since improved performance after initial issues. He clarified that asphalt work being done on a completed lane was to maintain traffic flow around flyover sections.

Let the critics go and verify. We’ve done one carriageway. Where asphalt is being reapplied, it’s around flyover intersections for smooth movement,” he said.

The minister reaffirmed his commitment to restoring public confidence in Nigeria’s road infrastructure, saying, “We want Nigerians to feel the impact of governance.

Advertisement

“President Tinubu is investing heavily in roads—North, South, East and West—because he understands the economy runs on infrastructure. I have never seen such a unique President.”
(PUNCH)

Advertisement

News

Sanwo-Olu makes U-turn, Unblocks Lawyer Who Sued Him Over Blocking On X

Published

on

Lagos State Governor, Babajide Sanwo-Olu, has unblocked human rights lawyer, Festus Ogun, on X after a meeting with him at Lagos House, Marina, on Friday.

The lawyer, who had accused the governor of rights violations, announced the development in a post on his X account on Saturday.

Advertisement

According to him, Sanwo-Olu personally invited him for a brief meeting to address his complaints.

Lagos Governor Babajide Sanwo-Olu has unblocked me on X (Twitter). I met briefly with him yesterday at Lagos House Marina, on his invitation, to amicably resolve my complaint of human rights violations. We will continue to hold authorities accountable, regardless. Aluta continua!” Ogun wrote.

READ ALSO:Lawyer Sues Sanwo-Olu For Blocking Him On X

Advertisement

Tribune Online reports that Ogun had earlier filed a suit against Sanwo-Olu at a Federal High Court in Lagos, accusing him of violating his fundamental rights by blocking him on his verified X account.

In the suit marked FHC/L/CS/1739/25, which he shared on Facebook, the lawyer claimed the governor blocked him over his 2021 “constructive criticisms” and “demand for accountability” on the October 2020 #EndSARS killings.

In 2021, I noticed that the Governor blocked me on his official X handle @jidesanwoolu owing to my constructive criticisms of his policies and demand for accountability in respect of the October 2020 #EndSARS Massacre.”

Advertisement

READ ALSO:‘Court Of Corruption’ — Obasanjo Knocks INEC Chairman, Judiciary In New Book

Ogun said the action has prevented him from accessing vital government updates and information.

“Blocking me on X has prevented me from accessing public updates and receiving information about policies and governance in Lagos, which constitutes a violation of my right to receive information without interference,” he said.

Advertisement

In his originating summons, he asked the court to declare the move unconstitutional, arbitrary, and discriminatory.

 

Advertisement
Continue Reading

News

Tragedy Deepens As Prime Suspect in Taraba Student’s Death Found Dead

Published

on

The investigation into the death of Comfort Jimtop, a 100-level Mass Communication student at Taraba State University, has taken a dramatic turn following the discovery of the lifeless body of Emmanuel Kefas, the prime suspect in the case.

Kefas’s body was discovered on Friday in the Tudiri community, Ardo-Kola Local Government Area, under unclear circumstances, intensifying public concern and adding a tragic dimension to a case that has already gripped the university community and residents across Taraba State.

Advertisement

Confirming the development on Saturday, the spokesperson for the Taraba State Police Command, James Lashen, said the police received a report from the village head of Tudiri about the discovery.

READ ALSO:Army Kills Notorious Bandit, Babangida, In Kogi

A lifeless body was found in Tudiri, and a Tecno Android phone was recovered beside it,” Lashen stated.

Advertisement

Upon charging the phone, investigators found a photograph showing the deceased with the late Comfort Jimtop, suggesting they were in a romantic relationship.”

Lashen added that the body has been taken to the Federal Medical Centre (FMC) in Jalingo for autopsy. At the same time, efforts are ongoing to officially identify the remains through the suspect’s family.

READ ALSO:Four Feared Killed As Gunmen Attack Burial Ceremony In Anambra

Advertisement

Police have yet to determine whether Kefas’s death was the result of suicide, homicide, or an accident. Investigations into both deaths are continuing.

Comfort Jimtop’s mysterious death had earlier sparked outrage on campus and across the state, with students and rights groups demanding justice. Kefas was named a prime suspect in the case, which remains open.

This latest development has left many unanswered questions and deepened the grief surrounding the case.

Advertisement

Students, residents, and civil society groups are closely monitoring the situation, calling on authorities to ensure a thorough investigation and bring clarity to the tragic chain of events.

Advertisement
Continue Reading

News

Ossiomo, Chinese Impasse: This Is Our Story — Management

Published

on

The management of Ossiomo Power Plant has cleared the air on the dispute between its Chinese partners and the circumstances surrounding the shutting down of the power plant early this month.

Representative of Ossiomo management, Engineer Festus Evbuomwan, during an interactive session with customers on the impasse between the two partners, said contrary to the rumour making the rounds, the management of Ossiomo Power Plant had paid over ₦2bn to its Chinese partner — Jiangsu Communication Clean Energy Technology (CCETC) — since the power plant started operation.

Advertisement

Recall that representative of CCETC who identified himself as Mr. ‘W’ had, during a telephone phone interview two weeks ago, claimed that “instruction to shutdown was because we lost lots of money and did not get any return on investment,” adding that “all the $20m investment was done by us including the distribution lines.”

But Evbuomwan during the interactive session, said the management was not aware of the $20m investment the Chinese partner claimed, just as he disclosed that “when they generate power, we sell and pay them.”

READ ALSO:Edo Govt Denies Shares As Ownership Tussle Rocks Ossiomo Power

Advertisement

He disclosed that after shutting down the power plant, the Chinese partners came up with a request of ₦185m to be paid to two Chinese not known to the management, stressing that this was declined.

According to him, the Chinese partner, having seen how lucrative the business is, “went to some quarters and raised some issues probably thinking they can manoeuvre us with the help of some big persons, so that they can use their machines to generate power and sideline us but this is not possible.”

The Chinese partners also claimed that they borrowed $20m from their native land to invest, we are not aware of such investment, and we do not know where the money was invested up till now.

Advertisement

“They have been also saying they have not been receiving anything, but I want to tell you unequivocally that first, the partners run a joint account where their investment is going into. More so, The Chinese partners have received over ₦2bn so far for the power they generate with their machines. When they generate the power, we sell and pay them.”

READ ALSO: Five Years After, Edo Govt Reconnects To BEDC As Ossiomo Shut Down

Engr. Evbuomwan, while apologising to customers for the power outage caused by the dispute between the two partners, said Ossiomo had started power generation though not in full capacity, assuring that power generation would be fully restored soon.

Advertisement

“We have purchased turbines, and one have started working. They are working on the second one, so, by the time our five turbines start working we will be in full capacity. Even with that, those connected to the government may not be reached immediately. This is because the government bought the poles and contracted the wiring, and we cannot force the government to do our bid. Also, we are making efforts to site 33kva transformer along Airport Road and Lagos Road as soon as possible, so that our customers there will get power.”

He said the Edo State government does not have a stake in the company, just as he appealed to the “government to let us supply power to customers in through their Lines. I want to emphasise that Ossiomo is not completely shut down.”

He further urged the “government to encourage the Nigerian citizens to invest and not to work against local investors.”

Advertisement

Continue Reading

Trending